Chile: Huatacondo remains offline after cyberattack
Huatacondo is still disconnected from Chile’s grid nearly three months after a cyberattack. Congress is demanding answers.
Chile’s Huatacondo solar plant in Tarapacá remains disconnected from the National Electric System nearly three months after a cyberattack. The grid operator activated safeguards to protect the network, and the case is still under investigation as lawmakers press the government for answers.
Update November 21, 2026: Nearly three months after the incident, Huatacondo still had not been reconnected to Chile’s National Electric System. The case also drew requests for explanations from the executive branch and reports of possible telecontrol failures at three other plants, although no link to the same attack has been confirmed.
The Huatacondo solar plant in Chile’s Tarapacá region remains disconnected from the country’s power grid after a cyberattack, and nearly three months later it still had not been restored to the National Electric System. The National Electricity Coordinator said it activated disconnection protocols to protect the grid and that the investigation remains open.
What is known about the affected facility?
Huatacondo has a capacity of 103 MW, and its associated BESS system is rated at 98 MW/312 MWh, according to pv magazine México. Available information describes it as a solar generation site with co-located storage, which extends the operational scope of the incident beyond the photovoltaic farm itself.
Shanghai Metals Market also reported that the BESS was still in commissioning, so its unavailability did not amount to a commercial operations outage. The same outlet said the Coordinator’s daily report listed zero availability for both the plant and the BESS under forced disconnection request SDCF 2026100475, registered on August 27.
What did the National Electricity Coordinator say?
The Coordinator confirmed that it activated disconnection protocols to protect the system and that the investigation remains open, according to pv magazine LATAM. The public information available in these sources does not say what the attack vector was or attribute responsibility.
The sources also do not include a full technical report on the internal impact to the infrastructure or the exact sequence of events that led to the disconnection. What they do show is that the preventive measure was aimed at isolating the facility to safeguard the operation of the power system.
What changed in the institutional response?
The case is no longer limited to grid operations, because lawmakers asked the executive branch for explanations about the incident, according to pv magazine México. That response broadens the political scope of the episode, although the sources reviewed do not detail any new official measures or the closure of the investigation.
What information is still missing?
The available sources do not provide enough public detail on the intrusion vector, attribution, or the technical impact of the cyberattack. The future of the investigation, and any eventual return of the plant to the grid, also remains open in the reporting cited here.
In parallel, 24 Horas reported that telecontrol failures may have been replicated at three other plants, but the available coverage does not provide enough detail to confirm whether they were tied to the same incident or identify those facilities. The reporting available focuses on the disconnection, the plant’s capacity and associated battery system, and the operator’s decision to prioritize protection of Chile’s power grid.
Sources
- Actualización: planta solar Huatacondo sigue desconectada tras ciberataqueprovectis.cl· Provectis
- La planta solar Huatacondo sigue desconectada en Chile y el Congreso pide explicaciones sobre el ciberataquepv-magazine-latam.com· pv magazine LATAM
- Ciberataques en Chile: el ataque que dejó desconectada una planta eléctrica y encendió las alarmast13.cl· T13
- Infraestructura crítica: de la respuesta a la investigaciónbiobiochile.cl· BioBioChile
- [SMM Flash] Chile's Huatacondo Solar Plant and Co-Located BESS Still Offline Nearly Three Months After Cyberattacknews.metal.com· Shanghai Metals Market
- Parque solar Huatacondo sigue fuera de servicio tras casi tres meses24horas.cl· 24 Horas
- La planta solar Huatacondo sigue desconectada en Chile y el Congreso pide explicaciones sobre el ciberataquepv-magazine-mexico.com· pv magazine México